Chapter 12
Civil Engineering Professional Practice and Miscellaneous
Nepal Telecom past exam questions
Past questions and answers
16 questions set from this chapter. Most repeated first.
- 2083 · 2nd Paper · 5 marks
What are the differences between one way slab and two way slab? Write.
Answer
Differences between One Way Slab and Two Way Slab
| S.N. | One Way Slab | Two Way Slab |
|---|---|---|
| 1 | The slab is supported on two opposite sides only. | The slab is supported on all four sides. |
| 2 | The load is transferred mainly in one direction, i.e. to the two supporting edges. | The load is transferred in both directions, i.e. to all four supporting edges. |
| 3 | The ratio of long span to short span is greater than or equal to 2 (L/S ≥ 2). | The ratio of long span to short span is less than 2 (L/S < 2). |
| 4 | Bending occurs mainly in one direction; hence main reinforcement is provided in one direction only. | Bending occurs in both directions; hence main reinforcement is provided in both directions. |
| 5 | Secondary/temperature reinforcement is provided in the transverse direction to hold the main bars and resist shrinkage and temperature stresses. | Both sets of bars act as main reinforcement; no separate secondary steel is needed in the same sense. |
| 6 | Deflection is comparatively more for the same span and thickness. | Deflection is comparatively less because the load is shared in two directions. |
| 7 | It requires less steel and simpler detailing, so it is more economical for long, narrow panels. | It requires more steel and more complex detailing, but is economical for square or nearly square panels. |
| 8 | Example: a verandah slab, a corridor slab, a cantilever-type long panel. | Example: a floor slab of a square room, a slab of a square hall. |
Note: In practice, a slab is designed as a two way slab when L/S < 2, and as a one way slab when L/S ≥ 2.
Answer checked by Claude Haiku · Oct 21, 2026
Test yourself · 2 MCQs
Loading…
- 2083 · 2nd Paper · 5 marks
Define Active and Passive Earth Pressure with figure.
Answer
Earth pressure is the lateral pressure exerted by soil on a retaining wall (or the pressure the wall exerts on the soil). Its value depends on how the wall moves. Rankine's theory is used here, assuming a smooth vertical wall, horizontal ground surface and cohesionless soil.
(a) Active earth pressure ()
The minimum lateral pressure, developed when the wall moves away from the backfill so that the soil expands and its shear strength is fully mobilised (the soil is on the point of failing by sliding down and outward behind the wall).
Pressure at depth : . Total thrust for a wall of height :
acting at above the base.
(b) Passive earth pressure ()
The maximum lateral pressure, developed when the wall moves towards the soil so that the soil is compressed until it is on the point of failing by being pushed up and out (for example, soil in front of a wall toe or anchor block).
acting at above the base.
Figure (schematic)
Active case (wall moves away) Passive case (wall moves toward soil)
|<-- soil wedge --> soil wedge -->|
|\ | /
| \ failure plane at | / failure plane at
| \ 45°+φ/2 to horizontal | / 45°-φ/2 to horizontal
H | \ ← Pa acts at H/3 H | / → Pp acts at H/3
|____\ |__/
wall moves ← wall moves →
The pressure diagram in each case is triangular, zero at the top and at the base.
Comparison
| Point | Active | Passive |
|---|---|---|
| Wall movement | Away from soil | Towards soil |
| Coefficient | ||
| Magnitude | Minimum | Maximum |
| Failure plane angle | ||
| Typical use | Design load on retaining wall | Resistance at toe, anchors, shear key |
For example, with : and , so passive pressure is nine times the active pressure.
Answer checked by Claude Sonnet · Oct 21, 2026
Test yourself · 2 MCQs
Loading…
- 2083 · 2nd Paper · 5 marks
Describe different types of soil based on particle size.
Answer
Types of Soil Based on Particle Size
Soil is classified on the basis of the size of its mineral particles. The three main separates are sand, silt and clay, and their relative proportions give the soil its textural class.
1. Sand (particle size 2.0 – 0.05 mm) Coarse, gritty particles visible to the naked eye. Sand has large pore spaces, so it drains water rapidly, holds little water and few nutrients, and warms up quickly. It gives good aeration but poor fertility.
2. Silt (0.05 – 0.002 mm) Intermediate-sized particles, smooth like flour when dry and slippery when wet. Silt retains more water and nutrients than sand but drains more slowly. It is easily eroded by water and forms a hard crust when dry.
3. Clay (below 0.002 mm) Extremely fine particles with a large surface area. Clay holds water and nutrients strongly, swells when wet and cracks when dry, and has very poor drainage and aeration. It is sticky when wet and hard when dry.
Textural classes (combinations)
| Class | Composition | Character |
|---|---|---|
| Sandy soil | Mostly sand | Light, droughty, low fertility |
| Clayey soil | Mostly clay | Heavy, waterlogged, sticky |
| Loamy soil | Balanced sand, silt and clay | Fertile, well-drained — best for crops |
| Sandy loam / silt loam / clay loam | Intermediate mixtures | Intermediate properties |
Conclusion: Particle size decides pore space, and hence drainage, aeration, water-holding capacity and fertility. Loamy soil, having a balanced mixture of all three separates, is the most suitable for plant growth.
Answer checked by Claude Haiku · Oct 21, 2026
Test yourself · 2 MCQs
Loading…
- 2083 · 2nd Paper · 5 marks
Describe the various internal effects developed in a structural member due to external loading.
Answer
Internal effects developed in a structural member due to external loading
When external loads act on a member, the member resists them by developing internal forces and deformations so that equilibrium is maintained. The main internal effects are:
-
Axial force (direct force) — acts along the longitudinal axis of the member. It is compressive when it tends to shorten the member (e.g. a column) and tensile when it tends to lengthen it (e.g. a tie rod). It produces axial (normal) stress and axial strain.
-
Shear force — the internal force acting parallel to the cross-section, tending to slide one part of the member over the adjacent part. It produces shear stress and shear deformation. In a simply supported beam under symmetrical load it is maximum at the supports and zero at mid-span.
-
Bending moment — the internal resisting couple developed when loads tend to bend the member. It produces bending (flexural) stress, compressive on one face and tensile on the other, and causes curvature. It is maximum where the shear force changes sign.
-
Torsion (twisting moment) — the internal torque developed when loads act eccentrically or about the longitudinal axis, tending to twist the member. It produces torsional shear stress and an angle of twist.
-
Deflection and deformation — the member changes shape: elongation or shortening under axial force, sagging or hogging under bending, and twist under torsion. Deflection must be kept within permissible limits for serviceability.
Note: Support reactions are external forces applied by the supports to the member, so they are not internal effects. They are determined first from equilibrium, and then the internal effects are found at sections of the member.
Conclusion: Axial force, shear force, bending moment and torsion give rise to axial, shear, bending and torsional stresses and corresponding strains. A member is designed so that these stresses and deformations stay within the permissible limits of the material.
Answer checked by Claude Sonnet · Oct 21, 2026
Test yourself · 2 MCQs
Loading…
- 2083 · 2nd Paper · 5 marks
What is Admixture? Write about any four types of admixtures.
Answer
Admixture is a material other than water, aggregate, cement (and, for some definitions, reinforcement) that is added to a concrete mix, either before or during mixing, in small quantities to modify the properties of fresh or hardened concrete — such as workability, setting time, strength, durability or appearance.
Four types of admixtures are:
-
Accelerating Admixture
These are added to speed up the setting and early strength development of concrete. They are useful in cold weather concreting. Example: calcium chloride, triethanolamine. -
Retarding Admixture
These delay the setting time of concrete. They are useful in hot weather, long-distance transportation, and large pours to avoid cold joints. Example: sugar, lignosulphonates. -
Air-Entraining Admixture
These introduce tiny air bubbles into concrete. They improve workability, resistance to freezing and thawing, and durability. Example: vinsol resin, synthetic detergents. -
Water-Reducing Admixture (Plasticizer)
These reduce the water requirement for a given workability or increase workability at the same water-cement ratio. They help in producing stronger, more durable concrete. Example: lignosulphonate-based plasticizers, superplasticizers.
Answer checked by Claude Haiku · Oct 21, 2026
Test yourself · 2 MCQs
Loading…
- 2083 · 2nd Paper · 5 marks
What are the characteristics of contour? How is it helpful in the engineering field? Clarify.
Answer
Characteristics of Contour
A contour line is an imaginary line on the ground joining points of equal elevation above a fixed datum. Its characteristics are:
- Equal elevation — Every point on a contour line has the same reduced level.
- Closed curves — Contours are always closed curves, either within the map or beyond its limits.
- Never cross each other — Two contours of different elevations cannot intersect (except in the rare case of an overhanging cliff or cave).
- Close spacing = steep slope — Contours close together indicate a steep slope; widely spaced contours indicate a gentle slope.
- Uniform spacing = uniform slope — Equally spaced contours represent a plane or uniform slope.
- Concentric closed contours — These indicate a hill or a depression. A hill is shown by higher values inside; a depression by lower values inside (shown with hachures).
- Perpendicular to the direction of steepest slope — Contours run at right angles to the line of maximum slope.
- Contours of the same elevation — A contour cannot have two different elevations; a contour line passing through a point represents only one elevation.
- Contours bend upstream at valleys — At a valley or stream, contours form a V-shape pointing upstream (uphill).
- Contours bend downstream at ridges — At a ridge, contours form a V-shape pointing downhill.
- Contours do not merge — They cannot merge or touch except in the case of a vertical cliff, where they coincide.
Helpfulness in the Engineering Field
Contours are of great use in surveying and civil engineering works:
- Selection of site — Helps select a suitable site for a dam, bridge, reservoir, road, canal or building by studying the terrain.
- Alignment of roads, railways and canals — A route with a permissible, economical gradient can be chosen by studying contour spacing (e.g. a contour map gives the best alignment for a road or canal).
- Reservoir and dam design — The contour map gives the capacity of a reservoir at different water levels and helps fix the dam height and location.
- Earthwork calculation — Volume of cut and fill for roads, canals and levelling works can be computed from contour maps.
- Drainage and irrigation — The direction of natural drainage and the slope available for irrigation canals can be determined.
- Town planning — Contour maps help plan roads, drainage, water supply and sewerage systems in hilly areas.
- Military use — Contours give information about the terrain for defence and strategic planning.
- Intervisibility of stations — Whether one station is visible from another can be checked from contour maps.
Thus, contours give a clear three-dimensional picture of the ground on a two-dimensional map and are indispensable for the planning and design of any engineering project.
Answer checked by Claude Haiku · Oct 21, 2026
Test yourself · 2 MCQs
Loading…
- 2083 · 2nd Paper · 5 marks
What is the difference between plain cement concrete and reinforced cement concrete? Give reasons for using steel as a reinforcing material.
Answer
Plain Cement Concrete (PCC) vs Reinforced Cement Concrete (RCC)
| Basis | Plain Cement Concrete (PCC) | Reinforced Cement Concrete (RCC) |
|---|---|---|
| Definition | Concrete of cement, sand, aggregate and water only, without any steel reinforcement | Concrete in which steel bars (reinforcement) are embedded to take up tensile stresses |
| Tensile strength | Very low (about 1/10th of its compressive strength) | High, because steel resists tension |
| Compressive strength | Good | Good (same concrete, plus steel) |
| Behaviour under load | Cracks and fails suddenly in tension zone | Cracks are controlled; members bend and carry load safely |
| Main use | Levelling course, bedding for footings, base of floors, mass concrete, kerbs | Footings, columns, beams, slabs, retaining walls, bridges |
| Cost | Cheaper | Costlier due to steel and skilled work |
| Thickness/ section | Requires large section to resist bending | Comparatively smaller section is sufficient |
Reasons for using steel as a reinforcing material
- High tensile strength — Steel has very high tensile strength, so it can safely take the tensile stresses which concrete cannot resist.
- Similar thermal expansion — The coefficient of thermal expansion of steel (≈12 × 10⁻⁶ /°C) is nearly equal to that of concrete, so both expand and contract together without internal cracking.
- Good bond with concrete — Steel develops a strong bond (bond stress) with concrete; the ribs of deformed bars improve this bond so that the two act as one composite material.
- Durability — When properly embedded with adequate cover, steel does not corrode and remains durable for the life of the structure.
- Easy to bend and shape — Steel can be easily cut, bent and tied into any required shape (stirrups, cranks, hooks) to suit the design.
- Fire resistance — Steel is protected by the surrounding concrete, which is a poor conductor of heat, so it retains its strength during fire.
- Economy — Steel is available in standard diameters and lengths and can be reused as scrap, making RCC economical in the long run.
Answer checked by Claude Haiku · Oct 21, 2026
Test yourself · 2 MCQs
Loading…
- 2083 · 2nd Paper · 10 marks
Define optimum moisture content (OMC) of soil. With the help of compaction curve, explain the relationship between the dry density and moisture content of soil. Discuss the engineering significance of optimum moisture content and maximum dry density in field compaction of soils.
Answer
(a) Definition of Optimum Moisture Content (OMC)
Optimum Moisture Content (OMC) is the moisture content of a soil at which, for a given compactive effort, the soil attains its maximum dry density. At this water content the soil particles are lubricated enough to slide past one another and pack closely, but the voids are not yet filled with water to the extent that water begins to occupy space that could otherwise be taken by soil solids. OMC is expressed as a percentage of the dry weight of soil.
(b) Compaction Curve and Relationship between Dry Density and Moisture Content
The relationship is obtained from the laboratory Proctor compaction test. Soil is compacted in a standard mould in layers with a standard rammer, at successively increasing water contents. For each trial the bulk density is measured and the dry density is computed as:
where γ_d = dry density, γ = bulk density, w = moisture content (as a decimal).
The values of w are plotted on the x-axis and the corresponding γ_d on the y-axis. The resulting curve is the compaction curve, which is roughly parabolic:
- Dry of optimum (w < OMC): The soil is stiff and the water film around particles is thin. Particle lubrication is insufficient, so friction and cohesion resist rearrangement. The entrapped air cannot escape easily and the soil remains loose; dry density is low. As water is added, the films thicken, friction reduces, particles slide into denser packing, and dry density increases.
- At optimum (w = OMC): The lubricating effect is maximum while air can still be expelled. The soil reaches its peak dry density — the Maximum Dry Density (MDD) — corresponding to the OMC.
- Wet of optimum (w > OMC): Water now occupies a large part of the void space and is relatively incompressible. The soil becomes soft and spongy; the rammer energy is absorbed by the water and pore pressure develops, so the soil cannot be densified further. Dry density falls.
Thus the curve rises to a peak at OMC and then falls, giving a unique OMC and MDD for each soil at a specified compactive effort. If the compactive effort is increased (heavier rammer or more blows), the curve shifts upward and to the left — MDD increases and OMC decreases.
(c) Engineering Significance in Field Compaction
- Specification of field water content: OMC tells the site engineer the water content at which the soil should be placed and rolled so that the required density is achieved with the least rolling effort. Field control is normally specified as OMC ± 2%.
- Attainment of MDD: Compacting near OMC gives the highest dry density, which means:
- Higher shear strength — greater bearing capacity for foundations, road subgrades and embankments.
- Lower permeability — reduced seepage through earth dams, canal banks and embankment cores.
- Less settlement — reduced void ratio means reduced consolidation settlement under load.
- Greater stability and durability — less volume change due to moisture variation (swelling/shrinkage).
- Control of construction cost: Since MDD is obtained at OMC, the number of roller passes and the compaction effort required are minimised, reducing time and cost.
- Quality control: The field dry density is compared with the laboratory MDD to compute the degree of compaction (usually required 95–100% of MDD). OMC serves as the reference for accepting or rejecting a compacted layer.
- Choice of compaction equipment: The shape of the compaction curve indicates whether the soil is well graded or uniform; this guides the selection of sheep-foot rollers, smooth-wheel rollers or vibratory rollers.
In short, OMC and MDD together form the basis for the field compaction specification, ensuring that the soil is placed at the right water content and compacted to the required density for safe and economical performance of the structure.
Answer checked by Claude Haiku · Oct 21, 2026
Test yourself · 2 MCQs
Loading…
- 2083 · 2nd Paper · 5 marks
Compare trenching and ducting methods used for underground cable networks.
Answer
Comparison of Trenching and Ducting Methods for Underground Cable Networks
Trenching (Direct Burial)
In this method, a trench of the required depth (usually 0.8–1.2 m) and width is excavated along the cable route, a sand bedding is laid, the cable is placed directly in the trench, and it is covered with sand, brick/tile protection and finally backfilled soil. The cable lies in direct contact with the surrounding soil.
Ducting
In this method, a duct (HDPE/PVC pipe, or a duct bank of several pipes) is first laid in the excavated trench and backfilled. Cables are then pulled or blown through these ducts. The cable does not touch the soil directly; it remains inside the duct.
Comparison
| Basis | Trenching (Direct Burial) | Ducting |
|---|---|---|
| Cable route | Cable laid directly in soil | Cable pulled through pre-laid ducts |
| Initial cost | Lower (no duct material) | Higher (cost of ducts and manholes) |
| Installation time | Faster for a single cable | Slower initially, but faster for later cables |
| Protection | Less mechanical protection; prone to damage by digging, rodents, soil movement | Good mechanical protection; safe from digging and rodents |
| Maintenance / repair | Difficult — full excavation needed to reach the cable | Easy — cable can be pulled out and replaced through manholes |
| Future expansion | Very difficult; new trench required for each new cable | Easy — spare ducts allow additional cables without re-excavation |
| Heat dissipation | Better (direct contact with soil) | Poorer (air gap inside duct reduces heat transfer) |
| Fault location | Comparatively difficult | Easier, as cable is accessible at manholes |
| Suitability | Rural/low-density areas, single cable, low budget | Urban/high-density areas, congested routes, multiple cables, areas with frequent road cutting |
Conclusion
Trenching is economical and simple for single-cable, low-traffic routes, while ducting, though costlier initially, is preferred in urban areas because it gives better protection, easier maintenance and provision for future cables.
Answer checked by Claude Haiku · Oct 21, 2026
Test yourself · 2 MCQs
Loading…
- 2083 · 2nd Paper · 5 marks
What kind of relationship should be between owner, contractor and engineer in construction organization? Explain briefly.
Answer
In a construction organisation, the owner, the contractor and the engineer must work in a professional, contractual and trust-based relationship, each with a distinct role defined by the contract. The relationship should be:
1. Contractual (legal) relationship The owner and the contractor are bound by a contract agreement (based on the tender, drawings, specifications, BOQ and conditions of contract). The engineer acts as the owner's representative and administers that contract. All three are thus linked through the same legal document, and duties, rights and liabilities flow from it.
2. Owner ↔ Engineer: principal and agent The engineer is appointed by the owner and works as the owner's technical representative/agent. The engineer plans, designs, prepares estimates and tender documents, supervises the work, certifies bills and advises the owner. The owner pays the engineer's fee and delegates authority, but the engineer must remain technically independent and honest.
3. Owner ↔ Contractor: employer and executor The owner provides the site, drawings, approvals and timely payment. The contractor executes the work as per drawings, specifications, quality standards and schedule. Their relationship is that of employer and contractor, governed strictly by the contract conditions.
4. Engineer ↔ Contractor: supervisor and supervised The engineer directs, inspects and controls the contractor's work, issues instructions, measures quantities and certifies payments. The contractor must follow the engineer's lawful instructions. The engineer must be fair, impartial and prompt — not hostile or biased — so that the contractor gets fair payment and the owner gets quality work.
5. Trust, cooperation and good faith All three parties should work with mutual trust, transparency and cooperation. Disputes should first be settled by mutual discussion, then by the engineer's decision, and finally by arbitration or the courts as per the contract. Delays in decisions, payments or approvals should be avoided, as they spoil the relationship and raise the cost and time of the project.
In short: the relationship should be contractual, clearly defined, cooperative and impartial, where the owner funds and owns the project, the contractor builds it, and the engineer independently supervises and certifies it — each respecting the other's rights and duties.
Answer checked by Claude Haiku · Oct 21, 2026
Test yourself · 2 MCQs
Loading…
- 2083 · 2nd Paper · 5 marks
Discuss the significance of specification of construction materials.
Answer
Specification of construction materials — significance (5 marks)
A specification is the written description of the quality, grade, strength, size, and standard of materials and workmanship required for a construction item. It forms a part of the contract document along with the drawings. Its significance:
-
Defines quality and grade — It states the exact quality of material to be used (e.g. OPC 43 grade cement conforming to NS 49, Fe 500 grade rebar conforming to NS 191), so the contractor cannot substitute inferior material.
-
Basis of cost estimate — The estimator prices the work from the specified quality and grade. Without specification, the tender amount cannot be compared or justified.
-
Legal and contractual control — It is the legal basis for accepting or rejecting materials and work. If the supplied material does not meet the specification, the engineer can reject it and the contractor must replace it at his own cost.
-
Uniformity and standardisation — It brings uniformity in materials and workmanship across different sites and agencies, and refers to national/international standards (NS, IS, ASTM) so that quality is measurable and testable.
-
Basis of quality control and testing — It fixes the tests and frequency (e.g. cube test of concrete, sieve analysis of sand, tensile test of steel), which helps the engineer accept or reject the material objectively.
-
Guidance to site staff and contractor — It tells the supervisor and the contractor exactly what to procure, how to store, and how to handle the material, reducing disputes and rework.
-
Durability and safety — Proper specification of materials ensures strength, durability, water-tightness and safety of the structure, and prevents premature failure.
In short, specification is essential for quality assurance, fair costing, smooth execution and legal protection in any construction work.
Answer checked by Claude Haiku · Oct 21, 2026
Test yourself · 2 MCQs
Loading…
- 2083 · 2nd Paper · 5 marks
Draw a line diagram to indicate various structures for drinking water from a source to a consumer household.
Answer
Line diagram: Drinking water supply system (source to consumer household)
(Source)
┌─────────────────┐
│ Spring / River / │
│ Lake / Tubewell │
└────────┬─────────┘
│
▼
┌─────────────────┐
│ Intake Structure│ ← collects water from source
└────────┬─────────┘
│
▼
┌─────────────────┐
│ Transmission │ ← conveys raw water (gravity/main)
│ Main / Conduit │
└────────┬─────────┘
│
▼
┌─────────────────┐
│ Sedimentation / │ ← removes suspended particles
│ Plain Basin │
└────────┬─────────┘
│
▼
┌─────────────────┐
│ Filtration Unit │ ← removes fine impurities
│ (Slow / Rapid) │
└────────┬─────────┘
│
▼
┌─────────────────┐
│ Disinfection │ ← chlorination / bleaching powder
│ (Chlorine Tank) │
└────────┬─────────┘
│
▼
┌─────────────────┐
│ Clear Water │ ← stores treated water
│ Reservoir (CWR) │
└────────┬─────────┘
│
▼
┌─────────────────┐
│ Distribution │ ← distributes to service areas
│ Main / Network │
└────────┬─────────┘
│
▼
┌─────────────────┐
│ Service │ ← branch pipe to street/community
│ Reservoir / │
│ Break Pressure │
│ Tank (BPT) │
└────────┬─────────┘
│
▼
┌─────────────────┐
│ Consumer │ ← tap at household
│ Household Tap │
└─────────────────┘
Main structures in sequence:
- Source – spring, river, lake or tubewell
- Intake – collects and protects water at the source
- Transmission main – carries raw water to treatment plant
- Treatment units – sedimentation, filtration, disinfection
- Clear water reservoir (CWR) – stores treated water
- Distribution main and network – conveys water to the locality
- Service reservoir / break pressure tank (BPT) – maintains pressure and storage
- Consumer household tap – final delivery point
Answer checked by Claude Haiku · Oct 21, 2026
Test yourself · 2 MCQs
Loading…
- 2083 · 2nd Paper · 5 marks
Find the ultimate load capacity for an axially loaded column when eccentricity does not exceed 5%.
Answer
For a short axially loaded reinforced concrete column, when the minimum eccentricity (e_{\min}) does not exceed (5%) of the lateral dimension (D), i.e.
[ e_{\min} \le 0.05D ]
the column is designed as an axially loaded column. Its ultimate load capacity is given by:
[ P_u = 0.4 f_{ck} A_c + 0.67 f_y A_{sc} ]
where:
- (P_u) = ultimate axial load capacity (N or kN)
- (f_{ck}) = characteristic compressive strength of concrete (N/mm²)
- (A_c) = net area of concrete (= A_g - A_{sc})
- (A_g) = gross area of column section (= bD)
- (f_y) = characteristic yield strength of reinforcement steel (N/mm²)
- (A_{sc}) = area of longitudinal reinforcement (mm²)
The coefficients (0.4) and (0.67) are the limit-state design factors for concrete and steel respectively. This formula is valid only when the column is short and the minimum eccentricity condition (e_{\min} \le 0.05D) is satisfied. If (e_{\min} > 0.05D), the column must be designed as an eccentric column.
Answer checked by Claude Haiku · Oct 21, 2026
Test yourself · 2 MCQs
Loading…
- 2083 · 2nd Paper · 5 marks
Briefly explain the things to be considered while designing a septic tank.
Answer
Things to be considered while designing a septic tank (5 marks)
-
Number of users and volume of sewage. The tank capacity is fixed from the number of persons using it and the daily flow of sewage. A minimum of 24-hour retention (detention) time is taken, and for a normal household the minimum liquid capacity is kept at about 2,000 litres (roughly 130–150 litres per person per day).
-
Number of chambers and sludge/soakage space. A two-chamber tank is preferred. The first chamber holds about two-thirds of the total volume for sludge digestion and the second chamber for clarified effluent. Sludge storage (clearing interval) of about 1–2 years must be provided so that the tank is desludged only at long intervals.
-
Depth, length and width (shape). The tank should be rectangular with a length-to-width ratio of about 2:1 to 3:1. Liquid depth is kept between 1.0 m and 2.0 m (usually 1.2–1.8 m), with freeboard of about 0.3 m above the liquid level. Too shallow a tank gives poor digestion; too deep a tank gives poor sludge collection.
-
Inlet and outlet arrangement. The inlet must discharge below the liquid surface and be provided with a dip or baffle (T-pipe) to prevent short-circuiting and to stop floating matter from escaping. The outlet should also be a submerged T-pipe or baffle, taking clarified effluent from the middle depth, with a slope of about 1 in 40 to 1 in 60 towards the soak pit or drain field.
-
Ventilation, gas escape and water-tightness. Provision must be made for the escape of gases (vent pipe) and for access manholes (at least 0.5 m × 0.5 m) over each chamber for inspection and desludging. The tank must be made water-tight (RCC or brick masonry with cement plaster) and located at a safe distance (generally not less than 15 m) from any drinking water source to avoid pollution.
Answer checked by Claude Haiku · Oct 21, 2026
Test yourself · 2 MCQs
Loading…
- 2083 · 2nd Paper · 10 marks
What is water cement ratio? Describe the various factors that affect the strength gain of concrete.
Answer
Water-cement ratio is the ratio of the mass (or volume) of water to the mass of cement in a concrete mix. It is the single most important factor controlling the strength of concrete. For ordinary work it is kept between 0.4 and 0.6; a lower ratio gives stronger, denser concrete but makes the mix less workable.
Abrams' law states that, for given materials and conditions, the strength of concrete is inversely proportional to the water-cement ratio. Excess water beyond that needed for hydration remains as capillary voids, which reduce strength and increase permeability.
Factors affecting the strength gain of concrete:
-
Water-cement ratio — The dominant factor. Lower w/c ratio → less capillary porosity → higher strength. Every 0.01 increase in w/c reduces strength by roughly 1–2%.
-
Cement content and type — More cement (at the same w/c) gives more cement paste and better binding. OPC gains strength faster than PPC; rapid-hardening cement gains early strength quickly.
-
Aggregate characteristics — Grading, shape, surface texture, and maximum size. Well-graded, angular, rough aggregates give better interlocking and strength; flaky and elongated particles reduce it. Larger maximum size allows a leaner mix.
-
Degree of compaction — Full compaction removes entrapped air. Every 1% of entrapped air reduces strength by about 5–6%. Vibration gives denser concrete than hand tamping.
-
Curing (moisture and temperature) — Hydration needs water. Inadequate curing stops hydration and causes shrinkage cracks. Ideal curing temperature is about 20–25°C; high temperature gives rapid early strength but lower ultimate strength, while low temperature (below about 5°C) almost halts hydration.
-
Age of concrete — Strength increases with age. Concrete gains about 70–80% of its 28-day strength in 7 days and continues to gain strength for years. The 28-day cube strength is the standard basis of design.
-
Admixtures — Water-reducing admixtures allow a lower w/c at the same workability (raising strength); accelerators speed up early strength; air-entrainers improve durability but slightly reduce strength.
-
Water quality and impurities — Clean potable water is required. Salts, silt, organic matter, or sugar in water retard setting and reduce strength.
-
Method of mixing and placing — Machine mixing is more uniform than hand mixing; over-mixing causes segregation. Proper placing without segregation and adequate compaction are essential.
-
Water-cement ratio at the point of use — Water added on site to improve workability (which raises the w/c) is a common cause of strength loss.
In summary, strength gain depends mainly on the water-cement ratio, compaction, and curing, with aggregate quality, cement type, age, and admixtures playing supporting roles.
Answer checked by Claude Haiku · Oct 21, 2026
Test yourself · 2 MCQs
Loading…
- 2083 · 2nd Paper · 10 marks
Define a contract in the context of construction works. Explain the different types of contracts (Item Rate, Lump Sum, Cost Plus and Percentage Rate contracts). Also, make a list of the essential conditions of contract.
Answer
Definition of Contract in Construction Works
A contract in construction works is a legally binding agreement between two or more parties (usually the Employer/Owner and the Contractor) by which the contractor agrees to execute a specified work — such as construction, repair or supply — within a stipulated time, in accordance with agreed drawings, specifications and conditions, in return for a consideration (payment) made by the employer. It creates legal rights and obligations on both parties and is enforceable by law.
Types of Contracts
1. Item Rate Contract (Unit Price Contract)
- The contractor quotes a rate per unit for each item of work (e.g., Rs per m³ of concrete, Rs per m² of plaster).
- Payment is made on the basis of the actual quantity of work measured at the quoted rates.
- Quantities are only approximate; the total amount is not fixed in advance.
- Suitable for: works where the nature of work is clear but quantities cannot be accurately estimated, and where variation in quantities is expected.
- Advantage: easy to adjust for changes in quantity; Disadvantage: final cost is uncertain.
2. Lump Sum Contract
- The contractor agrees to complete the entire work for a single fixed sum as per the drawings and specifications.
- Payment is made in instalments as per the progress of work (or on completion).
- Suitable for well-defined works where drawings and specifications are complete and clear, so that the scope is fully known.
- Advantage: owner knows the total cost beforehand; Disadvantage: risky for the contractor if quantities or conditions change, and disputes arise over extra work.
3. Cost Plus Contract
- The contractor is reimbursed the actual cost of labour, materials, plant and overheads, plus an agreed percentage or fixed fee as profit.
- Suitable for emergency works (flood damage, earthquake repair), works of uncertain nature, or where time is short and design is incomplete.
- Advantage: work can start early and quality can be maintained; Disadvantage: no incentive to reduce cost, so the owner may end up paying more.
4. Percentage Rate Contract
- The contractor quotes a percentage above or below the estimated cost (based on the schedule of rates prepared by the department).
- Payment = Estimated cost ± agreed percentage.
- Suitable for government/departmental works where a standard schedule of rates (e.g., DUDBC norms) exists.
- Advantage: simple to prepare and compare tenders; Disadvantage: the estimate must be accurate, otherwise the owner loses or the contractor gains unfairly.
Essential Conditions of Contract
- Offer and Acceptance — a valid offer by one party and its unconditional acceptance by the other.
- Legal Capacity of Parties — both parties must be competent (of legal age, of sound mind, not disqualified by law).
- Free Consent — consent must be free from coercion, undue influence, fraud or misrepresentation.
- Lawful Consideration — payment/consideration must be lawful and defined.
- Lawful Object — the purpose of the contract must be legal and not against public policy.
- Certainty of Terms — terms, scope, drawings, specifications and quantities must be clear and definite.
- Time of Completion — the period within which the work is to be completed, along with provisions for extension.
- Contract Sum and Payment Terms — total amount, mode, schedule and conditions of payment.
- Rights and Obligations of Parties — duties of employer and contractor clearly stated.
- Quality and Specification of Work — materials, workmanship and standards to be followed.
- Penalty and Liquidated Damages — provision for penalty for delay or defective work.
- Dispute Resolution and Arbitration Clause — method of settling disputes.
- Termination Clause — conditions under which the contract may be terminated.
- Signature and Witness — the contract must be signed, dated and witnessed by authorised persons.
Answer checked by Claude Haiku · Oct 21, 2026
Test yourself · 2 MCQs
Loading…
Questions from Nepal Telecom Lok Sewa Overseer 5th Level (Overseer (Level 5) · 2nd Paper · 2083). Answers are written for this site; check them against your class notes.