Chapter 15

Project Management

TU BBA past exam questions

Past questions and answers

16 questions set from this chapter. Most repeated first.

  • 2025 Model

Define a project.

Answer

A project is a temporary, one-time endeavour undertaken to create a unique product, service or result. It has a defined start and end, specific objectives, a limited budget and resources, and involves a set of interrelated activities performed by a team. Examples include constructing a hydropower plant or launching a new software system.

Answer checked by Claude Sonnet · Oct 21, 2026

Test yourself · 2 MCQs

Loading…

  • 2025 Model

List the various stages of a project life cycle.

Answer

The stages of a project life cycle are:

  1. Conceptualization (initiation) – the idea is identified, goals and feasibility are assessed.
  2. Planning – scope, schedule, budget, resources, risks and team are planned in detail.
  3. Execution (production) – the actual work is performed and the deliverables are created.
  4. Termination (closeout) – the project is completed, handed over, evaluated and resources are released.

Some models also add a separate monitoring and control phase running alongside planning and execution.

Answer checked by Claude Sonnet · Oct 21, 2026

Test yourself · 2 MCQs

Loading…

  • 2025 Model

Depict a specimen organization structure of a project organizational structure.

Answer

A specimen project organizational structure (project/matrix type) is shown below.

                 Top Management
                       |
                 Project Manager
        ---------------------------------
        |        |         |            |
   Engineering  Finance   Marketing   Procurement
   Specialists  Staff      Staff        Staff
   (Task A)    (Task B)   (Task C)     (Task D)

The project manager heads the project and coordinates specialists drawn from the functional departments. In a pure project structure these members report only to the project manager. In a matrix structure they report both to the functional head (for technical matters) and to the project manager (for project tasks).

Answer checked by Claude Sonnet · Oct 21, 2026

Test yourself · 2 MCQs

Loading…

  • 2025 Model

State any two circumstances in which matrix organizational structure is useful.

Answer

A matrix organizational structure is useful when:

  1. Several projects compete for scarce specialist resources. The organization runs multiple projects at once and cannot afford a full dedicated team for each, so experts are shared across projects.
  2. Projects require both strong technical depth and tight coordination. Functional departments maintain expertise while the project manager integrates work across departments, as in complex, multi-disciplinary projects.

Answer checked by Claude Sonnet · Oct 21, 2026

Test yourself · 2 MCQs

Loading…

  • 2025 Model

Highlight the major limitations of scoring models of project selection.

Answer

Major limitations of scoring models of project selection:

  • Subjectivity: criteria, weights and scores depend on the judgement of the evaluators and can be biased.
  • Assumed linearity: a higher score is assumed to mean a proportionally better project, which may not hold.
  • No absolute measure of value: scores are relative and do not show actual profit or return.
  • Weights are difficult to set and can be manipulated to favour a preferred project.
  • Ignores cost-benefit trade-offs and interdependence: costs are often treated as just another criterion, and interactions among criteria are overlooked.
  • False precision: numerical totals give an impression of accuracy that the inputs do not justify.

Answer checked by Claude Sonnet · Oct 21, 2026

Test yourself · 2 MCQs

Loading…

  • 2025 Model

Give the concept of project risk.

Answer

Project risk is an uncertain event or condition which, if it occurs, has a positive or negative effect on one or more project objectives such as scope, schedule, cost or quality. It combines the probability that an event will happen with the impact it would have:

Risk exposure=Probability of event×Impact\text{Risk exposure} = \text{Probability of event} \times \text{Impact}

Examples are cost overruns, delays, technical failure, and changes in regulations. Risk arises from uncertainty, so it must be identified, assessed and managed throughout the project life cycle.

Answer checked by Claude Sonnet · Oct 21, 2026

Test yourself · 2 MCQs

Loading…

  • 2025 Model

Mention any four common methods of project cost estimation.

Answer

Four common methods of project cost estimation:

  1. Analogous (top-down) estimation – using the actual cost of similar past projects.
  2. Parametric estimation – applying a statistical relationship between historical data and variables (e.g. cost per square metre).
  3. Bottom-up estimation – estimating each work package and summing up to get the project total.
  4. Three-point (PERT) estimation – using optimistic, most likely and pessimistic estimates: E=O+4M+P6E=\dfrac{O+4M+P}{6}.

(Expert judgement and learning-curve methods are also used.)

Answer checked by Claude Sonnet · Oct 21, 2026

Test yourself · 2 MCQs

Loading…

  • 2025 Model

What do you mean by critical path in a project network?

Answer

The critical path is the longest-duration sequence of connected activities from the start to the end of a project network. It determines the shortest possible time in which the project can be completed. Activities on it have zero slack (float), so any delay in them delays the whole project. Management therefore watches critical activities closely and may crash them to shorten the project.

Answer checked by Claude Sonnet · Oct 21, 2026

Test yourself · 2 MCQs

Loading…

  • 2025 Model

Mention the different pitfalls that can occur in a project team.

Answer

Common pitfalls in a project team:

  • Groupthink – the desire for harmony suppresses critical thinking and dissent.
  • Social loafing – some members contribute less because individual effort is not visible.
  • Unclear goals and roles – members are confused about responsibilities.
  • Conflict and poor communication – unresolved personal or task conflicts.
  • Lack of trust and commitment among members.
  • Poor leadership and weak decision making.
  • Dominance by a few members, ignoring others' views.
  • Loss of motivation due to unrealistic deadlines or lack of rewards.

Answer checked by Claude Sonnet · Oct 21, 2026

Test yourself · 2 MCQs

Loading…

  • 2025 Model

State the important decision rules that are used in deciding whether to terminate an ongoing project.

Answer

Important decision rules for terminating an ongoing project:

  1. Strategic fit: terminate if the project no longer supports the organization's strategy or priorities.
  2. Financial/economic criteria: terminate if the expected benefits no longer exceed the remaining cost (negative NPV on remaining investment), regardless of sunk cost.
  3. Technical feasibility: terminate if the technical objectives cannot be achieved.
  4. Schedule and cost performance: terminate if serious, uncorrectable overruns occur (e.g. by earned value indicators).
  5. Risk and external changes: terminate if risks become unacceptable or the market, law or technology changes.
  6. Better alternatives: terminate if resources can be used in a higher-value project.

Answer checked by Claude Sonnet · Oct 21, 2026

Test yourself · 2 MCQs

Loading…

  • 2025 Model

[6  5 = 30] Describe the socio-technical approach to project management. Explain how effective project management contributes to achieving strategic objectives of an organization. Describe the four key stages in project risk management and the steps necessary to manage risk. Why is it important to include contingency funding in project cost estimates? Explain. Explain the five stage model of team development. Describe the strategies for developing a high-performance project team. Distinguish among the four main forms of project termination.

Answer

(a) Socio-technical approach

Project management is not only technical (tools, scheduling, budgeting, planning) but also social (people, culture, politics). The socio-technical approach says both sides must be balanced.

  • The technical side covers the work breakdown structure, networks, scheduling, cost estimating, risk analysis and control systems.
  • The social side covers leadership, team building, conflict handling, stakeholder management, organizational culture and communication.

Technical tools fail when the human and organizational environment is ignored, and good relationships fail without planning and control. Effective project managers therefore apply both.

(b) Contribution to strategic objectives

Projects are the means by which strategy is put into action. Effective project management helps because it:

  • links project selection and priorities to strategic goals, so resources go to the right work;
  • delivers outputs on time, within budget and to the required quality, which supports competitive advantage;
  • allows faster response to market change and quicker product launches;
  • improves the use of scarce resources and reduces waste;
  • gives top management visibility and control through reporting and portfolio review;
  • builds learning and capability that can be reused.

(c) Four stages of risk management

  1. Risk identification: find possible risks using brainstorming, checklists, past projects and expert opinion.
  2. Risk assessment/analysis: estimate the probability and impact of each risk, rank them (risk matrix) and decide which matter most.
  3. Risk response development: choose a response of mitigation, avoidance, transfer (insurance, contracts) or acceptance, with contingency plans.
  4. Risk response control: put the plans into effect, monitor the risks, watch for new ones, update the risk register and report.

(d) Contingency funding

Contingency funds are needed because estimates are made under uncertainty. Unforeseen events, scope changes, price changes, estimation errors and risks that occur can raise costs. A contingency reserve:

  • stops the project from stalling or overrunning its approved budget;
  • gives realistic budgets and protects the project manager's credibility;
  • allows risks to be handled at once without a new approval process;
  • shows stakeholders openly that uncertainty exists.

It is normally set as a percentage of the estimate, according to the level of risk, and is controlled by the manager or sponsor.

(e) Five-stage model of team development (Tuckman)

  1. Forming: members meet, are polite and uncertain, depend on the leader, and roles are unclear.
  2. Storming: conflict over roles, leadership and methods; resistance to authority.
  3. Norming: rules, roles and norms are agreed; cohesion and trust grow.
  4. Performing: the team works efficiently with high commitment, autonomy and problem-solving.
  5. Adjourning: the project ends and the team disbands, with a review of achievements and recognition.

(f) Strategies for a high-performance team

  • Set a clear, shared vision and measurable goals.
  • Select members with the right skills and a good mix of roles.
  • Build trust and open communication, and hold regular meetings.
  • Define roles and responsibilities and give authority with accountability.
  • Provide training and development.
  • Reward team results and recognize contributions.
  • Manage conflict constructively and keep team spirit high.
  • Show leadership that is supportive and empowers members.

(g) Four main forms of project termination

  1. Termination by extinction: the project ends because it succeeded (completed, accepted) or because it failed or was stopped.
  2. Termination by addition: the project becomes a formal part of the parent organization, as a new department or division, with its staff and equipment.
  3. Termination by integration: resources, people and functions are absorbed into existing departments and the project disappears as a separate unit. This is the most common and difficult form.
  4. Termination by starvation: resources are cut gradually, so the project fades away without a formal decision to end it.

Answer checked by Claude Sonnet · Oct 21, 2026

Test yourself · 2 MCQs

Loading…

  • 2025 Model · 7 marks

Explain the elements in the project portfolio selection process and discuss how they work in a logical sequence to maximize a portfolio.

Answer

Project portfolio selection is the process of choosing the set of projects that best supports organizational strategy within limited resources. Its elements and their logical sequence are:

  1. Establish a strategic direction: top management sets mission, goals and strategy, which become the basis for choosing projects.
  2. Define project categories and criteria: projects are grouped (for example compliance, growth, cost reduction, R&D) and each category gets target proportions of the budget.
  3. Identify and gather proposals: a pool of candidate projects is collected with data on cost, benefits, risk and resource need.
  4. Screen and evaluate: proposals are checked with financial models (NPV, payback, IRR) and non-financial or scoring models for strategic fit, risk and feasibility.
  5. Balance the portfolio: the mix is balanced across risk, return, time horizon, technology and market, and checked against the strategy.
  6. Allocate resources and approve: funds and people are committed to the chosen projects and priorities are set.
  7. Monitor, review and adjust: the portfolio is reviewed regularly; projects are accelerated, changed or terminated as conditions change.

The steps work in sequence. Strategy sets the direction, the categories and criteria turn it into rules, screening picks the best candidates, balancing makes the whole set coherent, and review keeps it aligned. Together they maximize the strategic value and return of the portfolio rather than of each project alone.

Answer checked by Claude Sonnet · Oct 21, 2026

Test yourself · 2 MCQs

Loading…

  • 2025 Model · 7 marks

Explain the various types of project costs and highlight the key differences between them.

Answer

Main types of project costs:

  1. Direct costs: costs that can be traced to a specific work package or activity, such as labour, materials, equipment and subcontractors.
  2. Indirect (overhead) costs: costs of general support shared by several projects, such as rent, utilities, administration and supervision. They are allocated, not traced.
  3. Fixed costs: costs that do not change with the level of activity, such as equipment rent, licences and salaries of permanent staff.
  4. Variable costs: costs that change with output, such as materials and hourly labour.
  5. Recurring and non-recurring costs: recurring costs repeat in each unit or period (for example operating costs); non-recurring costs occur once (for example design, set-up).
  6. Sunk costs: costs already spent that cannot be recovered; they should not influence future decisions.
  7. Opportunity costs: the benefit lost by using resources on this project instead of the next best use.
  8. Contingency or reserve costs: funds set aside for uncertainty and unexpected events.

Key differences: direct costs are traceable while indirect ones are allocated; fixed costs are constant while variable costs move with activity; recurring costs repeat while non-recurring ones occur once; sunk costs are in the past and irrelevant to decisions, while opportunity costs are future and relevant.

Answer checked by Claude Sonnet · Oct 21, 2026

Test yourself · 2 MCQs

Loading…

  • 2025 Model · 7 marks

From the following information, develop an activity-on-node (AON) project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many days will the project take? ID Description Predecessor Time A Survey site None 2 B Excavate site A 4 C Install power lines B 3 D Install drainage B 5 E Pour foundation C, D 3

Answer

AON network: A -> B -> (C and D in parallel) -> E.

Forward pass (ES, EF)

  • A: ES 0, EF 2
  • B: ES 2, EF 6
  • C: ES 6, EF 9
  • D: ES 6, EF 11
  • E: ES = max(9, 11) = 11, EF 14

Backward pass (LF, LS)

  • E: LF 14, LS 11
  • D: LF 11, LS 6
  • C: LF 11, LS 8
  • B: LF = min(8, 6) = 6, LS 2
  • A: LF 2, LS 0

Slack (LS - ES)

ActivityDurationESEFLSLFSlack
A202020
B426260
C3698112
D56116110
E3111411140

Critical path: A - B - D - E (zero slack). Path length is 2+4+5+3=142+4+5+3 = 14.

The project will take 14 days. Activity C has 2 days of slack.

Answer checked by Claude Sonnet · Oct 21, 2026

Test yourself · 2 MCQs

Loading…

  • 2025 Model · 7 marks

Explain how earned value management (EVM) can be used in project evaluation and control. What are the key issues in the use of EVM?

Answer

Earned value management (EVM) integrates scope, schedule and cost to measure project performance objectively. It uses three basic values:

  • PV (planned value): budgeted cost of work scheduled.
  • EV (earned value): budgeted cost of work actually completed.
  • AC (actual cost): actual cost of work completed.

Use in evaluation and control

  • Schedule variance SV=EV−PVSV = EV - PV and schedule performance index SPI=EV/PVSPI = EV/PV show whether the project is ahead or behind schedule.
  • Cost variance CV=EV−ACCV = EV - AC and cost performance index CPI=EV/ACCPI = EV/AC show whether it is under or over budget.
  • Forecasts such as EAC=BAC/CPIEAC = BAC/CPI and ETC=EAC−ACETC = EAC - AC predict the final cost and the cost still to be spent.
  • Trends in the indices give early warning, so corrective action can be taken before the problems grow.
  • Results can be reported to management and clients in a common, comparable form across projects, and used to decide on re-planning or termination.

Key issues in using EVM

  • It needs a detailed WBS, a baseline budget and schedule, and a reliable cost-accounting system.
  • Measuring percent complete is often subjective (for example 50-50 rules, or progress claimed too early).
  • It measures cost and schedule only, not quality or scope satisfaction.
  • SPI in money terms is unreliable late in a project, and it does not show whether the delayed work is on the critical path.
  • It is costly and complex to set up and maintain, and needs training and top management support.
  • Poor data entry (late or inaccurate actual costs) distorts the results.

Answer checked by Claude Sonnet · Oct 21, 2026

Test yourself · 2 MCQs

Loading…

  • 2025 Model · 20 marks

Read the following study carefully and answer the questions that follow: Although the name Rolls-Royce is inextricably linked with its ultra-luxurious automobiles, the modern Rolls-Royce operates in an entirely different competitive environment. A leading manufacturer of power systems for aerospace, marine, and power companies, Rolls-Royce’s market is focused on developing jet engines for a variety of uses, both commercial and defense-related. In this market, the company has two principal competitors, General Electric and Pratt & Whitney (owned by United Technologies). There are a limited number of smaller niche players in the jet engine market, but their impact from a technical and commercial perspective is minor. Rolls-Royce, GE, and Pratt & Whitney routinely engage in fierce competition for sales to defense contractors and the commercial aviation industry. The two main airframe manufacturers, Boeing and Airbus, make continual multimillion-dollar purchase decisions that are vital for the ongoing success of the engine makers. Airbus, a private consortium of several European partner companies, has drawn level with Boeing in sales in recent years. Because the cost of a single jet engine, including spare parts, can run to several million dollars, winning large orders from either defense or commercial aircraft builders represents an ongoing challenge for each of the “big three” jet engine manufacturers. Airlines in developing countries can often be a lucrative but risky market for these firms. Because the countries do not maintain high levels of foreign exchange, it is not unknown, for example, for Rolls-Royce or its competitors to take partial payment in cash with assorted commodities to pay the balance. Hence, a contract with Turkey’s national airline may lead to some monetary payment for Rolls-Royce, along with several tons of pistachios or other trade goods! To maintain their sales and service targets, these jet engine makers routinely resort to creative financing, long-term contracts, or asset-based trading deals. Overall, however, the market for jet engines is projected to continue to expand at huge rates. Rolls-Royce anticipates a 20-year window with a potential market demand of 70,000 engines valued at over 400billionincivilaerospacealone.Whendefensecontractsarefactoredinaswell,therevenueprojectionsforjetenginesalesarelikelytobeenormous.AsRolls−Royceseesthefuture,thesinglebiggestmarketgrowthopportunityisinlarger,greaterthrustenginesthataredesignedtobepairedwithlargerjetaircraft.Rolls−Royceiscurrentlyengagedinaseriesofstrategicdecisionswiththepotentialforhugepayoffsorsignificantlosses.Itiscouplingitslatestenginetechnology,theTrentseries,withBoeingandAirbus’focusonmoreefficientdesigns.Airbus’A350andBoeing’s777and787arehighlypopularandstrong−sellingmodelsdesignedtomaximizetheefficienttransportationofairtravelersatthelowestcost.Togainmarketshareinpoweringthesejets,Rolls−RoycedevelopedthenewTrentXWBengine–theworld’smostefficientcommercialjetengine.Developmentoftheenginestartedin2005whenRolls−Royce’sengineerssatdownwithAirbustodesignanenginepowerful2enoughtoserviceitsA350XWB(ExtraWideBody)jet,anairframepoweredbyonlytwoengines.InorderforAirbusandBoeingtomaketheiraircraftattractivetoairlines,theseaircraftmustbeefficient(thatis,cheaptooperate)butalsopowerfulenoughtocarryalargepassengerload.Thedecisiontomakeaninitialinvestmentinnewenginetechnologycancostajetenginemanufacturerover400 billion in civil aerospace alone. When defense contracts are factored in as well, the revenue projections for jet engine sales are likely to be enormous. As Rolls-Royce sees the future, the single biggest market growth opportunity is in larger, greater thrust engines that are designed to be paired with larger jet aircraft. Rolls-Royce is currently engaged in a series of strategic decisions with the potential for huge payoffs or significant losses. It is coupling its latest engine technology, the Trent series, with Boeing and Airbus’ focus on more efficient designs. Airbus’ A350 and Boeing’s 777 and 787 are highly popular and strong-selling models designed to maximize the efficient transportation of air travelers at the lowest cost. To gain market share in powering these jets, Rolls-Royce developed the new Trent XWB engine – the world’s most efficient commercial jet engine. Development of the engine started in 2005 when Rolls-Royce’s engineers sat down with Airbus to design an engine powerful 2 enough to service its A350 XWB (Extra Wide Body) jet, an airframe powered by only two engines. In order for Airbus and Boeing to make their aircraft attractive to airlines, these aircraft must be efficient (that is, cheap to operate) butalso powerful enough to carry a large passenger load. The decision to make an initial investment in new engine technology can cost a jet engine manufacturer over 1 billion in non-recoverable costs. As a result, it is critical that Rolls-Royce and its competition make the right strategic decisions about which aircraft to support. Recall from our project profile at the beginning of the chapter that Rolls-Royce invested in servicing the A380 double-decker airplane, whose disappointing sales may result in its cancellation. This potential cancellation will have a serious impact on Rolls-Royce’s bottom line. Rolls-Royce’s decision to pursue engine design efficiency that pairs up with the Airbus and Boeing models represents a strategic choice for the future. Rolls-Royce anticipates that the commercial passenger market will triple in the next 20 years. As a result, future opportunities will involve more economically viable aircraft. Boeing, Airbus and Rolls-Royce have all collectively taken a large financial gamble that their strategic vision of the future is correct. Questions
  1. Who are Rolls-Royce’s principal project management stakeholders? How would you design stakeholder management strategies to address their concerns?
  2. Given the financial risks inherent in developing a jet engine, make an argument, either pro or con, for Rolls-Royce to develop strategic partnerships with other jet engine manufacturers in a manner similar to Airbus’s consortium arrangement. What are the benefits and drawbacks in such an arrangement? 3

Answer

1. Principal stakeholders and strategies

Principal stakeholders:

  • Airframe manufacturers (Airbus, Boeing) – the customers; they decide which engine powers their aircraft.
  • Airlines (including those in developing countries) – end buyers who want efficient, reliable engines and flexible financing.
  • Defense contractors and governments – defense customers and regulators.
  • Shareholders and investors – concerned with returns on a $1 billion plus investment.
  • Competitors (GE, Pratt & Whitney) – influence market share and pricing.
  • Suppliers and partners, employees and engineers, regulators/aviation authorities and local communities.

Stakeholder management strategies: first identify stakeholders, then analyse their power, interest and expectations (power/interest grid), and manage each group accordingly.

  • Airbus/Boeing (high power, high interest): manage closely through joint design teams (as with the A350 XWB since 2005), long-term contracts, and regular progress reviews.
  • Airlines: offer creative financing, long-term service contracts, asset-based trading deals, and strong after-sales support.
  • Shareholders: transparent reporting, risk-sharing arrangements and clear strategic justification for large investments.
  • Regulators: early engagement on certification and safety.
  • Suppliers/employees: clear contracts, communication and incentives.
  • Keep a communication plan and review stakeholder positions throughout the project.

2. Strategic partnerships (argument in favour)

I argue for partnerships, because engine development costs over $1 billion in non-recoverable costs and outcomes depend on uncertain aircraft sales (as the A380 shows).

Benefits:

  • Shared financial risk and investment.
  • Pooled technical expertise and faster development.
  • Access to wider markets and customers.
  • Economies of scale in manufacturing and supply.
  • Stronger bargaining position with airframers.

Drawbacks:

  • Reduced control over decisions and design.
  • Sharing profits and intellectual property, with risk of leaking know-how.
  • Conflicts of culture, goals and management among partners.
  • Slower decision making and coordination costs.
  • Dependence on partners and reduced competitive independence.

Overall, the benefits of risk sharing outweigh the drawbacks if the agreement clearly defines roles, IP rights and governance.

Answer checked by Claude Sonnet · Oct 21, 2026

Test yourself · 2 MCQs

Loading…

Questions from TU BBA 2025 Seventh Semester Business Ethics (TU board exam, November 2025), TU BBA 2024 Seventh Semester Business Ethics (TU board exam, March 2024), TU BBA 2024 Seventh Semester Consumer Behaviour (TU board exam, March 2024), TU BBA 2025 Seventh Semester Consumer Behaviour (TU board exam, November 2025), TU BBA 2025 Seventh Semester Distribution Management (TU board exam, November 2025), TU BBA 2025 Seventh Semester Fundamentals of Advertising (TU board exam, November 2025), TU BBA 2024 Seventh Semester Fundamentals of Selling (TU board exam, March 2024), TU BBA 2025 Seventh Semester Fundamentals of Selling (TU board exam, November 2025), TU BBA 2023 Seventh Semester Investment Analysis (TU board exam, January 2023), TU BBA 2025 Seventh Semester Investment Analysis (TU board exam, November 2025), TU BBA 2024 Seventh Semester Service Marketing (TU board exam, March 2024), TU BBA 2025 Seventh Semester Working Capital Management (TU board exam, November 2025), TU BBA 2025 Seventh Semester Commercial Bank Management (Model Question) (TU model question, 2025 (set 1)), TU BBA 2025 Seventh Semester Fundamentals of Cooperatives Management (Model Question) (TU model question, 2025 (set 1)), TU BBA 2025 Seventh Semester Working Capital Management (Model Question) (TU model question, 2025 (set 1)), TU BBA 2025 Seventh Semester Investment Analysis (Model Question) (TU model question, 2025 (set 1)), TU BBA 2025 Seventh Semester Consumer Behaviour (Model Question) (TU model question, 2025 (set 1)), TU BBA 2025 Seventh Semester Fundamentals of Selling (Model Question) (TU model question, 2025 (set 1)), TU BBA 2025 Seventh Semester Sales Management (Model Question) (TU model question, 2025 (set 1)), TU BBA 2025 Seventh Semester Fundamentals of Advertising (Model Question) (TU model question, 2025 (set 1)), TU BBA 2025 Seventh Semester Corporate Accounting (Model Question) (TU model question, 2025 (set 1)), TU BBA 2025 Seventh Semester Budgeting (Model Question) (TU model question, 2025 (set 1)), TU BBA 2025 Seventh Semester Taxation in Nepal (Model Question) (TU model question, 2025 (set 1)), TU BBA 2025 Seventh Semester Corporate Accounting (Model Question) (TU model question, 2025 (set 2)), TU BBA 2025 Seventh Semester Project Management (Model Question) (TU model question, 2025 (set 1)) and TU BBA 2025 Seventh Semester Business Ethics (Model Question) (TU model question, 2025 (set 1)). Answers are written for this site; check them against your class notes.