  • 2082 · 2nd Paper · 10 marks

Explain Cash Flow, Time Value of Money, Simple Payback Period and Discounted Payback Period that are generally encountered when appraising a project.

Answer

Cash Flow

Cash flow is the net movement of cash into and out of a project over a period of time. It is the basic unit of project appraisal, because a project is judged by the actual cash it generates, not by accounting profit.

Net Cash Flow (NCF)=Cash Inflows−Cash Outflows\text{Net Cash Flow (NCF)} = \text{Cash Inflows} - \text{Cash Outflows}

  • Inflows: revenue from electricity sales, salvage value of assets, recovery of working capital, grants.
  • Outflows: initial investment (plant, transmission lines, substations), operating and maintenance costs, taxes, interest and loan repayments.

Cash flows are arranged as a cash flow stream by year: a large negative flow at the start (Year 0), then positive flows during the operating life. Two conventions are used:

BasisTreatment of interest and depreciation
Equity / Net cash flowInterest and loan repayment are deducted; depreciation ignored (non-cash)
Project / Free cash flowInterest ignored (financing decision separated); depreciation ignored

Depreciation is excluded because it is a book entry, not a cash transaction. Cash flow is the raw input for every appraisal technique — payback, NPV, IRR and benefit–cost ratio all work on cash flows, not on accounting profit.


Time Value of Money (TVM)

Time value of money is the principle that Rs 1 received today is worth more than Rs 1 received in the future, because today's money can be invested to earn a return, and because of inflation and risk.

Reasons: (i) earning capacity / opportunity cost, (ii) inflation erodes purchasing power, (iii) uncertainty of future receipts, (iv) preference for present consumption.

Compounding (moving forward in time):

FV=PV(1+i)nFV = PV(1+i)^n

Discounting (bringing future cash to present value):

PV=FV(1+i)n=FV×DFPV = \frac{FV}{(1+i)^n} = FV \times DF

where ii = discount rate (cost of capital), nn = number of years, and DF=1/(1+i)nDF = 1/(1+i)^n is the discount factor.

For a series of equal annual cash flows (annuity):

PV=A×(1+i)n−1i(1+i)nPV = A \times \frac{(1+i)^n - 1}{i(1+i)^n}

Example: At i=10%i = 10\%, Rs 1,00,000 received after 3 years is worth today PV=1,00,000/(1.10)3=Rs 75,131PV = 1{,}00{,}000 / (1.10)^3 = \text{Rs } 75{,}131.

Significance: TVM is the foundation of discounted appraisal. It allows cash flows occurring in different years to be brought to a common base (present value) so that projects of different size, life and timing can be compared. It also gives the decision rules: accept a project if NPV > 0 or IRR > cost of capital.


Simple Payback Period (PBP)

Definition: The time required for the cumulative net cash inflows to recover the initial investment exactly. It measures liquidity and risk, not profitability.

Formula (equal annual cash flows):

PBP=Initial InvestmentAnnual Net Cash Inflow years\text{PBP} = \frac{\text{Initial Investment}}{\text{Annual Net Cash Inflow}} \text{ years}

Formula (unequal cash flows): cumulate the inflows year by year until the investment is recovered, then interpolate:

PBP=A+BC\text{PBP} = A + \frac{B}{C}

where AA = last full year before recovery, BB = unrecovered amount at start of that year, CC = cash inflow of the recovery year.

Example: Investment Rs 10,00,000; inflows Rs 3,00,000, Rs 4,00,000, Rs 4,00,000, Rs 2,00,000.

YearInflow (Rs)Cumulative (Rs)
13,00,0003,00,000
24,00,0007,00,000
34,00,00011,00,000

Recovery falls in Year 3. Unrecovered at start of Year 3 = Rs 3,00,000.

PBP=2+3,00,0004,00,000=2.75 years=2 years 9 months\text{PBP} = 2 + \frac{3{,}00{,}000}{4{,}00{,}000} = 2.75 \text{ years} = 2 \text{ years } 9 \text{ months}

Decision rule: Accept if PBP ≤ the firm's predetermined cut-off period; among alternatives, the shorter PBP is preferred.

Merits: Simple, easy to compute and explain; measures liquidity and how long capital stays at risk; useful where technology or demand is uncertain.

Demerits: Ignores time value of money; ignores all cash flows after the payback date, so it may reject a project with a large later return; the cut-off period is arbitrary.


Discounted Payback Period (DPBP)

Definition: The time required to recover the initial investment from the present value of net cash inflows, i.e. the simple payback period adjusted for the time value of money. It is a stricter, more realistic measure than PBP.

Procedure:

  1. Compute the discount factor for each year at the given discount rate ii.
  2. Multiply each year's cash inflow by its discount factor to get the discounted cash flow (DCF).
  3. Cumulate the DCFs until the initial investment is recovered; interpolate for the fraction of the year.

Example: Investment Rs 10,00,000; discount rate 10%; same inflows as above.

YearInflow (Rs)DF @ 10%DCF (Rs)Cumulative DCF (Rs)
13,00,0000.90912,72,7272,72,727
24,00,0000.82643,30,5796,03,306
34,00,0000.75133,00,5269,03,832
42,00,0000.68301,36,60210,40,434

Unrecovered at start of Year 4 = Rs 10,00,000 − Rs 9,03,832 = Rs 96,168.

DPBP=3+96,1681,36,602=3.70 years=3 years 8.4 months\text{DPBP} = 3 + \frac{96{,}168}{1{,}36{,}602} = 3.70 \text{ years} = 3 \text{ years } 8.4 \text{ months}

Decision rule: Accept if DPBP ≤ the cut-off period; prefer the shorter DPBP.

Merits: Recognises the time value of money; still gives a simple "years to recover" figure; useful for ranking projects under capital rationing and for judging risk exposure.

Demerits: Still ignores cash flows beyond the payback date; requires an assumed discount rate; the cut-off remains subjective. It is always longer than the simple PBP, so a project may pass PBP but fail DPBP.


Summary comparison

BasisSimple PBPDiscounted PBP
Time value of moneyIgnoredConsidered
Cash flows usedUndiscountedDiscounted at cost of capital
Result in example2.75 years3.70 years
Main useLiquidity and risk screeningLiquidity plus profitability screening

For a project such as a hydropower or transmission scheme in NEA, cash flows are first projected over the construction and operating periods, then discounted at the cost of capital; PBP and DPBP give a quick indication of how long the utility's funds remain at risk, while NPV and IRR give the final accept/reject decision.